Wisconsin Street Realignment Project
3/15/2024
The long-awaited and highly anticipated Wisconsin Street Realignment Project is finally ready to move forward! You may have noticed that North Fork Enterprises has started preparing for the project already, including mobilizing equipment, locating and relocating utilities, staking and survey work, and setting up traffic control.
Demolition of the old car wash, clearing, and grubbing are scheduled to start Tuesday, March 19, and the project is anticipated to be completed by May 16, 2024. To view the project plans, please click the following link: Project Plans & Contracts | LHTAC
We understand that construction projects can be disrupting to business and daily life, but we appreciate your understanding during this process. If you have any questions, please feel free to reach out.